Cost overruns in central infrastructure projects
Copy link to Cost overruns in central infrastructure projectsMains
The Ministry of Statistics and Programme Implementation (MoSPI) reports every month on the delays and costs of central projects of ₹150 crore and above.
What changed
25 Jun 2026Briefnewly addedIn May 2026 the cost overrun on 1,987 ongoing projects was about ₹5.4 lakh crore. Delays in land acquisition, clearances and funding raise the cost of projects. Mains: Delays that raise the cost of projects lower the return on public capital spending. News Arena India, 25 Jun 2026: Major infra projects log ₹5.4 lakh crore cost overrun (MoSPI May report) (opens in a new tab)
Also filed elsewhere
- Green status for nuclear power · on Climate finance, carbon markets and carbon pricing
Green status for nuclear power would class nuclear energy as green, so that nuclear projects could raise money through green instruments.