Science and Technology › Energy technology
हिन्दी — Read in HindiGrid, power sector and energy policy
The power sector: the grid and its transmission corridors, the regulators and distribution companies, market reforms, and what solar and wind change about running the grid. It serves GS3 answers on energy infrastructure.
Foundation note: The grid: how power reaches a plug, who regulates it, and what renewables change
Curtailment
Copy link to CurtailmentPrelims and Mains
LeadThe grid is the limit: 300 GW and curtailmentAugust 2026
Why in news
India's non fossil capacity crossed 300 GW on 31 July 2026, and renewables supplied a record 20 per cent of generation in July. In the same weeks solar plants were being told to switch off output, because the grid could not carry it.
- 300.50 GWnon fossil capacity, over 54 per cent of installed capacity
- 500 GWthe target for non fossil capacity by 2030
- 20 per centrenewables' share of generation in July 2026, a record
- 30 to 50 per centoutput lost by projects on temporary grid access
Background
- Installed capacity is what plants could produce at full output, measured in gigawatts; generation is the electricity they actually deliver.
- Solar and wind run only when the weather allows, so their share of generation is far below their share of capacity.
- Solar output peaks at midday, while Indian demand peaks after sunset.
- India reached 50 per cent non fossil capacity five years ahead of its 2030 target.
What curtailment is
- Curtailment is the deliberate cutting of a plant's output below what it could generate, because the grid cannot absorb or carry the power.
- The generator is usually not compensated for the power it was ready to supply.
- Projects connected on temporary network access lose the most, 30 to 50 per cent of their output.
- New auctions have slowed, and 40 to 45 GW of awarded capacity has no signed power purchase agreement.
Why a solar heavy grid is harder to run
- A coal or hydro turbine is a heavy spinning mass, and that inertia steadies the grid's frequency by itself.
- Solar and wind are inverter based resources: they reach the grid through power electronics and give no such inertia.
- The result is lower grid strength, with voltage and frequency less stable.
- The answers are grid forming inverters and synchronous condensers.
The remedies
- Transmission: lines built ahead of the plants, as under the Green Energy Corridor.
- Storage: batteries and pumped storage carry midday power into the evening.
- Demand: time of day tariffs, daytime charging of electric vehicles and industrial use moved into solar hours.
- Payment: treating curtailment as a grid service that is compensated.
The way forward
- Plan transmission and generation together, so that no plant is finished before its line.
- Require storage with new solar, as the floating solar scheme already does.
- Use the existing grid better, since new lines alone cannot keep pace with new capacity.
Prelims facts
- Non fossil capacity includes solar, wind, hydro, bio power and nuclear.
- India's target is 500 GW of non fossil capacity by 2030.
- Solar is the largest part of non fossil capacity.
- Inertia comes from rotating turbines, not from solar panels.
Solar and wind generate when the weather allows rather than when demand asks, and Indian demand peaks after sunset while the panels work at midday. Where neither the wires nor the load can take the power, the cheapest answer is to switch some of it off: curtailment, deliberately cutting a plant's output below what it could generate, with the loss falling on the generator. The remedies are to move demand into solar hours through industrial electrification, workplace charging and time of day tariffs, to store the surplus in batteries and pumped storage, and to treat curtailment as a paid grid service rather than an uncompensated loss.
- Mains: India needs both new transmission lines and smarter use of the existing grid, since new lines alone cannot keep pace with renewable additions.
Four grid routes
| Route | What it does | Capacity it could enable |
|---|---|---|
| Batteries at renewable plants | Stores output so connections used about 25 per cent of the time carry power two to three times as much | About 400 GW |
| Renewables at underused coal plant connections | Uses spare capacity on connections coal plants already hold | About 100 GW |
| New connections at existing substations, with batteries | Adds connections at substations already built | About 100 GW |
| Reconductoring | Replaces sagging conductors with high temperature, low sag ones on the same towers | Nearly doubles line capacity |
What changed
20 Aug 2026LeadThe grid is the limit: 300 GW and curtailment
- Hybrid renewable energy project
- A plant that generates from more than one renewable source, usually solar and wind, on one site and through one grid connection.
- Evacuate
- In the power sector, to carry electricity away from where it is generated to where it is consumed.
- Inverter based resource
- A generator such as solar or wind that reaches the grid through power electronics, and so gives none of the rotating inertia that coal and hydro turbines do.
- Power purchase agreement
- A long term contract under which a buyer, usually a distribution company, agrees to take a project's electricity at an agreed price.
- Power exchange
- A platform for generators, distribution companies, traders and large consumers to buy and sell electricity.
- Market coupling
- Discovering one electricity price across exchanges through a centralised mechanism.
Also filed elsewhere
- India's data centre capacity · on Semiconductors, computing hardware and data centres
A data centre is counted in megawatts of IT load, because uninterrupted power is what it must be given and constant cooling is what that power becomes.